Tuesday, July 16, 2013

Value Management


CONCEPT OF VALUE

The concept of value can be defined as the relationship between satisfying
an organization’s many conflicting needs and the resources required
to meet those needs.
Value can be added to projects in several ways. These include providing
greater levels of client satisfaction, maintaining acceptable levels of
satisfaction while lowering resource expenditures, or some combination of
the two. It is also possible to improve value by simultaneously increasing
satisfaction and resources, provided that satisfaction increases more than
the resources used to achieve it.
When managing projects for value, five fundamental concepts must be
embraced.


Concept #1: Projects derive their value from the benefits the organization
accrues by achieving its stated goals—Remember that projects are typically
initiated as a perceived solution to a goal, need, or opportunity.
Thus, when we want to determine the degree to which a project is being
managed for ‘‘value,’’ it is critical to first ensure that the project falls
in line with organizational goals. Projects that are being run counter to
a firm’s stated goals (e.g., customer satisfaction, commercial success, or
improving health and safety) already fail the first test of value.
Concept #2: Projects can be viewed as investments made by management
Any investment comes with an expected return for the risk undertaken, and projects are no exception. Because they consume
resources and time, they are expected to yield acceptable returns, based
on internal requirements, along with associated benefits.
Concept #3: Project investors and sponsors tolerate risk—There are
inherent risks in projects, because there is considerable uncertainty
surrounding their outcomes. These risks may be technical (‘‘Does the
technology that is driving the project work?’’), they may be commercial
(‘‘Will the project succeed in the marketplace?’’), they may involve health
and safety issues (‘‘Can we manage the project within appropriate safety
parameters?’’), or some combination of all of the above. Accepting these
risks is recognition that each project is a unique endeavor with unique
unknowns. Investors may not be able to manage these risks, but they
do tolerate them because the potential rewards may far outweigh the
negative impact.
Concept #4: Project value is related to investment and risks
This fourth concept defines project value as a function of the resources
committed (investment made) and the extent of risks taken. Goodpasture
puts it this way: ‘‘The traditional investment equation of ‘total return
equals principal plus gain’ is transformed into the project equation of
‘project value is delivered from resources committed and risks taken.’’’3
Using these terms, we can see that value will always walk a narrow
line between expected return on investment and risk. When the equation
gets out of balance; that is, when the perceptions of the organization are
that the expected return cannot make up for excessive levels of risk, the
project ceases to produce value. The implication of this concept is that different
projects require different levels of investment with varying levels
of risk. Consequently, the value delivered by each of these projects will
also vary.

Concept #5: Value is a balance among the three key project elements:
performance, resource usage, and risk—Again, if we employ a ‘‘ledger’’
mindset, we can add up the credit column to include drawbacks such
as expenditure (resource usage) and risk accepted. Balanced against
these ‘‘negatives’’ is the company’s expectation of project performance
and positive outcomes. Naturally, the higher the expected performance of
the project, the greater the resource usage and risk a company is willing
to commit.

For most project organizations, the objective measure of value is in
monetary terms. This is because projects consume time, and the longer
it takes to complete the project, the less valuable the money spent.
Therefore, when evaluating a project’s value, the concept of the time
value of money should be taken into account. In addition, monetary
measures allow project managers to acknowledge the future uncertainty
of outcomes by evaluating the financial impact of risk events.
The measures of net present value (NPV), economic value add, and
expected monetary value (EMV) take both of these factors into account.
Net present value, is significant in
that successful projects have a positive NPV over their life cycle. Both
NPV and economic value add employ the discounted cash flow concept;
however, economic value add is a financial measure of project performance
after the project becomes operational. It is defined as the difference between the present value of after-tax earnings from the project and the
benefits from the next-best investment alternative. The logic underlying
economic value add is that if the projected after-tax earnings are less than
the cost of the capital the project consumes, then some other, less-risky
investment alternative may be more attractive. Expected monetary value is also the most appropriate financial measure
when measuring future uncertainty, or when multiple project
outcomes are possible, each with a different cost and schedule. It is
defined as the summation of the value of each outcome in dollars ($),
weighted by the probability of that outcome. For example, consider a
project that needs to be redesigned, and assume that the new approach
involves some risk to accomplish this goal. One possible monetary outcome
is $200,000 with a 40 percent probability of achieving this outcome,
while anothermonetary outcome is $150,000 with a 60 percent probability
of occurrence. The EMV of this project is
EMV = $200,00 0.4 + $150,000 0.6 = $170,000
If the NPV for this project is also positive, and if all other considerations
are equal, it is worth taking the risk of adopting the new approach to
redesign this project.

Key Principles of VM
The value management approach hinges on three key principles4:
1. An unending quest for enhancing value for the organization, establishing
metrics or estimates of value, and monitoring and controlling
them
2. A focus on clear definition of objectives and identification of targets
before seeking solutions
3. A focus on function, pivotal to maximizing those outcomes that are
innovative, meaningful, and practical

THE VM PROCESS
The detailed VM process and the typical terms used at different stages
of a project are illustrated in the Figure 8.3. Because the elements of
the figure are straightforward, we will focus our discussion of the process
from a strategic perspective. The elements of value management can be
grouped into five major categories:14
Needs assessment—This phase is concerned with arriving at a shared
understanding of the needs of various project stakeholders, the critical
success factors with the expected benefits defined qualitatively,
and the key performance indicators of time, cost, quality, or functionality,
defined through quantitative measures.
Idea generation—In this phase, the cross-functional team focuses
on generating creative and innovative alternatives to complete the
project.
Detailed evaluation—During this phase, the alternatives generated
in the previous phase are evaluated in detail in terms of their feasibility,
achievability, and potential contribution to expected project
benefits. At this stage, modifying alternatives to develop additional
options is also considered.
Optimum choice—This phase prioritizes the various alternatives and
selects the best alternative.
Feedback and control—This phase is the formal evaluation and
control process with feedback loops to improve the overallVMprocess.
During this phase, VM practitioners and users must obtain feedback
on its performance to ascertain whether the expected improvement
in value was realized, and to generate other good ideas that can be
adopted and implemented. During the feedback process, factors to
be assessed include the stakeholders’ judgment, involvement, and
support; the system’s appropriateness, use, and effectiveness; and
change management. Actions that can emerge from the feedback
stage include changes to personnel, approach, or the system, and
even repeating the VM exercise as a whole.

0 comments:

Post a Comment