- Determine the availability
of the resources
- Show the availability
as a percentage of the effort required to achieve the work package
- Duration =
(Effort/Productivity)/Availability
▫
If effort is in # of hours, the duration will be in # of hours
▫
To have duration in days, divide the value calculated above by the
number of working hours per day
- Cost = Duration* Unit
cost
▫
Cost = (Effort/Productivity ) * Unit cost
▫
Determine duration as per number 3 above
▫
Unit cost : e.g. $40/hour
Determining Durations of Work packages
•
PERT of each work package:
•
PERT of the entire project is the sum of the PERTs of all the
activities on the critical path
•
Standard Deviation of a work package:
PERT, Sigma and probabilities
•
50% probability that a task’s duration equals
its PERT
•
68% probability that a task’s duration is
between ( PERT + 1 * Sigma) and (PERT – 1 * sigma)
•
95% probability that a task’s duration is
between ( PERT + 2 * Sigma) and (PERT – 2 * sigma)