Estimating Work Duration


  1. Determine the availability of the resources
  2. Show the availability as a percentage of the effort required to achieve the work package
  3. Duration = (Effort/Productivity)/Availability
        If effort is in # of hours, the duration will be in # of hours
        To have duration in days, divide the value calculated above by the number of working hours per day
  1. Cost = Duration* Unit cost
        Cost = (Effort/Productivity ) * Unit cost
        Determine duration as per number 3 above
        Unit  cost : e.g. $40/hour



Determining Durations of Work packages
        PERT of each work package:
              
        PERT of the entire project is the sum of the PERTs of all the activities on the critical path
        Standard Deviation of a work package:
              
PERT, Sigma and probabilities
        50% probability that a task’s duration equals its PERT
        68% probability that a task’s duration is between ( PERT + 1 * Sigma) and (PERT – 1 * sigma)
        95% probability that a task’s duration is between ( PERT + 2 * Sigma) and (PERT – 2 * sigma)