What is the difference between PERT MEAN and Most Likely?

It is the contingency of a work package
0

PERT

A technique for estimating when there is uncertainty with the individual activity estimates.

Purpose: Knowing the weighted average and variances for each activity allows the project planner to compute the probability of meeting different project duration.
0

Thursday, October 4, 2012

PERT—Program Evaluation Review Technique


Assumes each activity duration has a range that statistically follows a beta distribution.
Uses three time estimates for each activity: optimistic, pessimistic, and a weighted average to represent activity durations.
Knowing the weighted average and variances for each activity allows the project planner to compute the probability of meeting different project durations.