It is the contingency of a work package
Showing posts with label PERT. Show all posts
Showing posts with label PERT. Show all posts
Wednesday, December 10, 2014
PERT
A technique for estimating when there is uncertainty with the individual activity estimates.
Purpose: Knowing the weighted average and variances for each activity allows the project planner to compute the probability of meeting different project duration.
Purpose: Knowing the weighted average and variances for each activity allows the project planner to compute the probability of meeting different project duration.
Thursday, October 4, 2012
PERT—Program Evaluation Review Technique
•Assumes each activity duration
has a range that statistically follows a beta distribution.
•Uses three time estimates for
each activity: optimistic, pessimistic, and a weighted average to represent
activity durations.
–Knowing
the weighted average and variances for each activity allows the project planner
to compute the probability of meeting different project durations.