•Assumes each activity duration
has a range that statistically follows a beta distribution.
•Uses three time estimates for
each activity: optimistic, pessimistic, and a weighted average to represent
activity durations.
–Knowing
the weighted average and variances for each activity allows the project planner
to compute the probability of meeting different project durations.