Wednesday, December 10, 2014

What is the difference between PERT MEAN and Most Likely?

It is the contingency of a work package
0

PERT

A technique for estimating when there is uncertainty with the individual activity estimates.

Purpose: Knowing the weighted average and variances for each activity allows the project planner to compute the probability of meeting different project duration.
0

Probability of completing the project

The Z value - tells us the probability of completing the project in the time specified.
0

Tuesday, December 9, 2014

Risk Quantification Analysis

Purpose of risk quantification:

  1. To get a numerical estimate f the overall effect of risk on the project objectives.
  2. Performed on risks that have been prioritized as potentially and substantially impacting the project's competing demands.
Why PMs conduct risk quantification?
  • To establish odds of achieving project goals
  • To justify contingency reserves
  • To validate time, cost, and scope targets
  • To conduct in depth "what if" analyses
Quantitative Risk Analysis eg: Monte Carlo simulation, Decision tree analysis.
  • Gives you - How likely is success?
  • How much contingency?
  • Which risks are high priority?


Tools and techniques used: 
  1. Data gathering and representation techniques
    1. Expert Interviews
    2. Probability Distributions
  2. Quantitative Risk Analysis and Modeling Techniques
    1. Modeling and Simulation
    2. Sensitivity Analysis
    3. Expected Monetary Value Analysis
  3. Expert Judgement
0

Purpose of assessing overall risk...


  1. Build support for less risky projects and cause cancellation for some higher -risk projects.
  2. Compare projects and help set relative priorities.
  3. Provide data for renegotiating over-constrained project objectives
  4. Assist in determining management reserve. 
  5. Facilitate effective communication and build awareness of project risk.
0

How do you determine the probability and impact of each risk?


  1. Analysis of plans and related documents
  2. Comparisons with similar systems
  3. Data from engineering or other models
  4. Experience and interviewing
  5. Modeling and simulation
  6. relevant lessons-learned studies
  7. Results from test and prototype development
  8. Sensitivity analysis of alternatives and inputs
  9. Specialist and expert judgments
0

Risk Management


  1. Risk qualitative Analysis: Evaluates key characteristics of individual risks enabling them to be prioritized for further action.  Select risk characteristics => Collect and analyze data => Prioritize Risks => Categorize risk causes => Document results.
  2. Qualitative risk ratings: An indication of the potential impact of risks on a project.  Typically a measure of the following characteristic; probability , Impact.  Typically expressed as Low, Medium, High.
    • High Risk: 50% or higher ( Likely)
    • Medium Risk : Between 10% and 50% ( Unlikely)
    • Low Risk: 10% or lower ( Very unlikely)
      • High probability can be expressed 
        • as a %
        • As a values statement
        • As a comparison
        • As a frequency
0

Risk identification output

Risk identification output is the RISK REGISTER:


  1. List of all risks ( properly stated)
  2. Risk owners
  3. Cause ( if known)
  4. Effect ( if known)
  5. Trigger Event ( signals the occurrence of risk)
  6. Preliminary Responses
0

Root Cause Analysis and Identification


  • Can be used for risk discovery 
  • Start with stating an outcome the project intends to avoid
  • Then work backwards to uncover sources that could cause the problem


Describing a risk event: 

Cause =>  Risk => Effect