It is the contingency of a work package
Wednesday, December 10, 2014
PERT
A technique for estimating when there is uncertainty with the individual activity estimates.
Purpose: Knowing the weighted average and variances for each activity allows the project planner to compute the probability of meeting different project duration.
Purpose: Knowing the weighted average and variances for each activity allows the project planner to compute the probability of meeting different project duration.
Probability of completing the project
The Z value - tells us the probability of completing the project in the time specified.
Tuesday, December 9, 2014
Risk Quantification Analysis
Purpose of risk quantification:
- To get a numerical estimate f the overall effect of risk on the project objectives.
- Performed on risks that have been prioritized as potentially and substantially impacting the project's competing demands.
Why PMs conduct risk quantification?
- To establish odds of achieving project goals
- To justify contingency reserves
- To validate time, cost, and scope targets
- To conduct in depth "what if" analyses
Quantitative Risk Analysis eg: Monte Carlo simulation, Decision tree analysis.
- Gives you - How likely is success?
- How much contingency?
- Which risks are high priority?
Tools and techniques used:
- Data gathering and representation techniques
- Expert Interviews
- Probability Distributions
- Quantitative Risk Analysis and Modeling Techniques
- Modeling and Simulation
- Sensitivity Analysis
- Expected Monetary Value Analysis
- Expert Judgement
Purpose of assessing overall risk...
- Build support for less risky projects and cause cancellation for some higher -risk projects.
- Compare projects and help set relative priorities.
- Provide data for renegotiating over-constrained project objectives
- Assist in determining management reserve.
- Facilitate effective communication and build awareness of project risk.
How do you determine the probability and impact of each risk?
- Analysis of plans and related documents
- Comparisons with similar systems
- Data from engineering or other models
- Experience and interviewing
- Modeling and simulation
- relevant lessons-learned studies
- Results from test and prototype development
- Sensitivity analysis of alternatives and inputs
- Specialist and expert judgments
Risk Management
- Risk qualitative Analysis: Evaluates key characteristics of individual risks enabling them to be prioritized for further action. Select risk characteristics => Collect and analyze data => Prioritize Risks => Categorize risk causes => Document results.
- Qualitative risk ratings: An indication of the potential impact of risks on a project. Typically a measure of the following characteristic; probability , Impact. Typically expressed as Low, Medium, High.
- High Risk: 50% or higher ( Likely)
- Medium Risk : Between 10% and 50% ( Unlikely)
- Low Risk: 10% or lower ( Very unlikely)
- High probability can be expressed
- as a %
- As a values statement
- As a comparison
- As a frequency
Risk identification output
Risk identification output is the RISK REGISTER:
- List of all risks ( properly stated)
- Risk owners
- Cause ( if known)
- Effect ( if known)
- Trigger Event ( signals the occurrence of risk)
- Preliminary Responses
Root Cause Analysis and Identification
- Can be used for risk discovery
- Start with stating an outcome the project intends to avoid
- Then work backwards to uncover sources that could cause the problem
Describing a risk event:
Cause => Risk => Effect