What is the Project Net Work?
Project network is a network of activities to complete the project. It is a flowchart of activity that graphically depicts the sequence, inter dependencies and start and finish date of the projects It also includes the leads, lags, duration of the projects etc.
Project network is a network of activities to complete the project. It is a flowchart of activity that graphically depicts the sequence, inter dependencies and start and finish date of the projects It also includes the leads, lags, duration of the projects etc.
•Provides the basis for scheduling
labor and equipment.
•Enhances communication among
project participants.
•Provides an estimate of the
project’s duration.
•Provides a basis for budgeting
cash flow.
•Identifies activities that are
critical.
•Help managers get and stay on
plan.
What is an Activity?
An activity is part of the project network. It is an element of project that requires time.
Merge Activity?
An activity which follows a series of activities. A series of activities merging into one activity.
–an
activity that has two or more preceding activities on which it depends.
Parallel / Concurrent Activities?
Two or more activities occurring at the same time.
–Activities
that can occur independently and, if desired,
not at the same time.
not at the same time.
Path ?
A sequence of connected dependent activities.
Critical Path?
A longest path of a project network. Has no slacks.
–the
longest path through the activity network that allows for the completion of all
project-related activities; the shortest expected time in which the entire
project can be completed. Delays on the critical path will delay completion of
the entire project.
Multiple number of activities following one activity.
–an
activity that has more than one activity immediately following it (more than
one dependency arrow flowing from it).
Basic Rules to follow in Developing Project Networks?
Each activity will have a unique number. Numbers will increase as the diagram progresses. No loops.
1.Networks typically flow from left
to right.
2.An activity cannot begin until
all preceding connected activities are complete.
3.Arrows indicate precedence and
flow
and can cross over each other.
and can cross over each other.
4.Each activity must have a unique
identify number that is greater than any of its predecessor activities.
5.Looping is not allowed.
6.Conditional statements are not
allowed.
7.Use common start and stop nodes.
ES, EF, ET, LS, SF, SL?
ES: Early Start
EF: Early Finish
ET: Estimated Time Duration for that activity
LS: Late Start
LF: Late Finish
SL: Slack
Forward Pass Computation?
–How soon can the activity start?
(early start—ES)
–How soon can the activity finish?
(early finish—EF)
–How soon can the project finish?
(expected time—ET)
•Add activity times along each
path in the network (ES + Duration = EF).
•Carry the early finish (EF) to
the next activity where it becomes its early start (ES) unless…
•The next succeeding activity is a
merge activity, in which case the largest EF of all preceding activities is
selected.
–How late can the activity start?
(late start—LS)
–How late can the activity finish?
(late finish—LF)
–Which activities represent the
critical path?
–How long can activity be delayed?
(slack or float—SL)
•Subtract activity times along
each path in the network (LF - Duration = LS).
•Carry the late start (LS) to the
next activity where it becomes its late finish (LF) unless
•The next succeeding activity is a
burst activity, in which case the smallest LF of all preceding activities is
selected.
Sensitivity?
–The
likelihood the original critical path(s) will change once the project is
initiated.
–The
critical path is the network path(s) that has (have) the least slack in common.
Activities on critical path.
Have no slack
Laddering?
–Activities
are broken into segments so the following activity can begin sooner and not
delay the work.
Lags?
Use of Lags?
–The
minimum
amount of time a dependent activity must be delayed to begin or end.
•Lengthy activities are broken
down to reduce the delay
in the start of successor activities.
in the start of successor activities.
•Lags can be used to constrain
finish-to-start, start-to-start, finish-to-finish, start-to-finish, or
combination relationships.
Hammock activity?
–An
activity that spans over a segment of a project.
–Duration
of hammock activities is determined
after the network plan is drawn.
after the network plan is drawn.
–Hammock
activities are used to aggregate
sections of the project to facilitate getting
the right amount of detail for specific sections
of a project.
sections of the project to facilitate getting
the right amount of detail for specific sections
of a project.
0 comments:
Post a Comment